Enow International Limted.
This is the large-scale municipal engineering projects where the hub will become the local landmark upon completion of the construction and thus the generator must go through the strict technical inspection before installed in the station hub. Fire-fighting equipment must always remain functional due to the crowded condition in the hub. Therefore, the 400kVA generator must satisfy the power demand from 4 fire-fighting pumps to operate simultaneously and emergency guidance system. In order to supply generators which operate stably, Kusing proposed a solution which adopts YTO’s engine, China company and open skid mounted genset, equipped with automatic transfer switch as well as measures such as automatic fueling system, two-stage muffling, smoke and dust treatment, noise reduction treatment via inlet and outlet channel, heat treatment, oil and gas emission treatment, etc. It was approved by the government authority and the hub was brought into operation with our generator solution.